Volume IVCoastal Beneficiation & Magnetite Upgrading Facility
18. Upgrading Plant Capital Expenditure (CAPEX) & Operating Cost (OPEX) Structure
Pages 297–320 · 24 pages in this chapter320 / 530
Sources
Scope & Subject Matter
- Class 5 Conceptual Capital Cost Estimate (AACE International guidelines, accuracy range pm 30 ext{--}40%):
- Major mechanical equipment package: Spirals, ball mills, Eriez magnetic separators, slurry pumps, filter presses.
- Electrical infrastructure, switchgear, substations, and standby power.
- Civil works, ground improvement, concrete foundations, and structural steel.
- Total estimated plant CAPEX range: US50.0 million to US55.0 million (excluding land acquisition and off-site grid interconnects).
- Unit Operating Costs (OPEX):
- Electrical power consumption (kWh per metric ton of product).
- Grinding media (forged steel balls) and liner wear consumption rates.
- Direct labor, plant maintenance, assay laboratory, and environmental monitoring costs.
- All-in sustaining coastal processing cost per dry metric metric ton (DMT) of finished concentrate.
Technical specification
Upgrading plant
- Capacity
- 1,000 TPD finished concentrate
- Feed
- ~5,600 TPD
- Classification
- Spiral separators
- Regrind
- Ball mill, P80 45–75 µm
- Cleaning
- 3-stage LIMS to ≥62–65% Fe
- TiO₂
- ≤ 4.5%
- Water
- Zero-effluent closed loop
- CAPEX
- US$50–55M (Class 5)
Interactive · mass balance
Upgrading plant throughput calculator
Concentrate
1,002 TPD
Tailings
4,598 TPD
Export concentrate
702 TPD
Pellet plant feed
301 TPD
Annual: 330.8 kt concentrate · 231.6 kt export · 99.2 kt to pelletizing. Defaults reflect the 1,000 TPD design on ~5,600 TPD feed and the 70/30 split.