Volume IVCoastal Beneficiation & Magnetite Upgrading Facility
15. Upgrading Plant Conceptual Engineering, Site Selection & Master Layout
Pages 241–256 · 16 pages in this chapter256 / 530
Sources
Scope & Subject Matter
- Plant site evaluation criteria: Proximity to AFTAA 09-I mining blocks, coastal bathymetry for barge berthing, road connectivity, power grid access.
- Plant footprint and master plot plan:
- Raw ore receipt dock and run-of-mine (ROM) stockpile yard.
- Spiral gravity separation building.
- Regrind and fine milling circuits.
- Multi-stage magnetic separation and cleaner banks.
- Concentrate thickening, vacuum filtration, and covered storage sheds.
- Tailings dewatering, dry stacking / reclamation sand storage, and water clarification plant.
Technical specification
Upgrading plant
- Capacity
- 1,000 TPD finished concentrate
- Feed
- ~5,600 TPD
- Classification
- Spiral separators
- Regrind
- Ball mill, P80 45–75 µm
- Cleaning
- 3-stage LIMS to ≥62–65% Fe
- TiO₂
- ≤ 4.5%
- Water
- Zero-effluent closed loop
- CAPEX
- US$50–55M (Class 5)
Interactive · mass balance
Upgrading plant throughput calculator
Concentrate
1,002 TPD
Tailings
4,598 TPD
Export concentrate
702 TPD
Pellet plant feed
301 TPD
Annual: 330.8 kt concentrate · 231.6 kt export · 99.2 kt to pelletizing. Defaults reflect the 1,000 TPD design on ~5,600 TPD feed and the 70/30 split.